Project Includes:

  • Construction of approximately 4km of 12-way 25kV distribution concrete-encased duct bank.
  • Installation of 17 thru-type and 7 tee-type precast electrical manholes.
  • Installation of FRE ducts and hangers over two bridge crossings at Serpentine River & Channel .
  • Final restoration works including asphalt pavement and curbs.

Project Details

Location

Surrey, BC

Date of Construction

2024